How do I schedule an inspection on a permit in SDL Desktop?
In the Construction module, this can be done two ways.
Option 1: From the Permit
- Open the permit and go to the Inspections tab.
- Click New for a single inspection, or check Multiple New to schedule several subcodes at once (select which subcodes need inspections).
- Enter the date, time, inspection type, and inspector for each.
Option 2: From the Inspections Data Grid
- Go to Construction > Inspections data grid.
- Click New in the toolbar.
- Enter the permit number and click Get Info to pull it up.
- Choose the subcode(s), date, time, inspection type, and inspector.