Skip to content
English
  • There are no suggestions because the search field is empty.

How do I schedule an inspection on a permit in SDL Desktop?

In the Construction module, this can be done two ways.

Option 1: From the Permit

  1. Open the permit and go to the Inspections tab.
  2. Click New for a single inspection, or check Multiple New to schedule several subcodes at once (select which subcodes need inspections).
  3. Enter the date, time, inspection type, and inspector for each.

Option 2: From the Inspections Data Grid

  1. Go to Construction > Inspections data grid.
  2. Click New in the toolbar.
  3. Enter the permit number and click Get Info to pull it up.
  4. Choose the subcode(s), date, time, inspection type, and inspector.